Which is an activity in the implementation lifecycle for a permanent P3O?
A.
Return staff members to operational roles
B.
Run an office through to delivery
C.
Close down a Programme Office
D.
Deliver capability Realize benefits
The Answer Is:
D
This question includes an explanation.
Explanation:
The P3O® Foundation (2013) manual lists delivering capability and realizing benefits as an activity in the permanent P3O implementation lifecycle. Section 4.3.5 states, "The implementation lifecycle for a permanent P3O includes delivering capability and realizing benefits as it transitions to operational status." This differs from returning staff (A), running an office (B), or closing a Programme Office (C), which relate to temporary models. The 2013 edition focuses on this phase to establish and validate the P3O’s operational effectiveness, ensuring long-term value. This activity supports strategic alignment.
[Reference: P3O® Foundation (2013) manual, Section 4.3.5, AXELOS. , ]
P3O-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"