A cost centre manager's performance is monitored based on a comparison of actual and budgeted...

A cost centre manager's performance is monitored based on a comparison of actual and budgeted cost. A summary performance report for the latest period is shown below.

The actual costs include:

*$28,000 for allocated head office costs.

*$18,000 payment for a rental agreement entered into by the cost centre manager two years ago.

*$34,000 for depreciation.

What is the cost centre manager's controllable actual cost for the period?

Give your answer to the nearest $000.