The programme is in the first tranche. The programme manager met with the project managers from the Employment Contracts and Call Centre Rationalization projects as well as the BCM. Many topics were discussed. After the meeting, the programme manager reviewed the information gathered at the meeting.
Which information should result in an addition to the risk register?