Which of following is part of critical benefits validation test?
A.
Currency
B.
Accurate
C.
Attribution
D.
Availability
The Answer Is:
C
This question includes an explanation.
Explanation:
The four critical tests for benefits validation are Description, Observable outcomes, Attribution, and Measurement. "Attribution" assesses whether the programme is genuinely responsible for the benefit. The MSP Practitioner confirms,"Four tests of business validation are: Description, Observable outcomes, Attribution and Measurement,"emphasizing the importance of validating benefits to ensure they result directly from programme activities.