Tom, a Procurement Manager, is initiating aSupplier Rationalisationproject.

Tom, a Procurement Manager, is initiating aSupplier Rationalisationproject. What should he completefirstto direct the project?

A.

Introduce Six Sigma

B.

Implement Total Quality Management

C.

Conduct SWOT Analysis

D.

Perform Spend Analysis