ISTQB CTAL-TM Question Answer
You are the Test Manager for a new product that is being developed according to an iterative lifecycle. At this point, you have 100% of your smoke tests automated, 20%
of your functional tests and 50% of your regression tests. Your iterations are four weeks long. You are finding that with each iteration significant maintenance is required
for your automated tests and you are not able to complete the testing within the planned timeframe. The test plan you created at the beginning of the project indicates
that all automated tests should be run before any manual tests.
Which of the following is a reasonable change to this plan based on how the project is going? [2]