A software development team has just completed the planning phase of a project when management...

A software development team has just completed the planning phase of a project when management recommends additional requirements. The team’s best response to this request would be to

A.

perform an impact analysis and adjust the plan accordingly

B.

agree to introduce the new requirements on the next version release

C.

outsource the new requirements to a subcontractor and manage it as a subordinate project

D.

adjust the resources and budget to maintain the project’s schedule and due date with the new requirements