A company uses four components (W. X. Y. and Z) to create its final product. The source and time factors for these components are listed below. What is die critical path for this company's final product?
ComponentSourceAcquisition TimeInstallation TimePredecessor Steps
WInternaln/a4 weeksNone
XExternal5 weeks4 weeksNone
YInternaln/a4 weeksW.X.Z
ZInternaln/a6 weeksNone