ASQ CQE Question Answer
A company decides to adopt a total quality system and has started the process by developing quality policies. Rank in order, from first to last, the rest of the steps that need to be performed to implement this system.
1.Audit the system
2.Determine system requirements
3.Develop a measurement system
4.Perform continuous improvement activities