APICS CPIM-ECO Question Answer
The next job to be performed was selected because it had the least amount of operation time prior to the due date. Which of the following priority sequencing rules was being used?
APICS CPIM-ECO Question Answer
The next job to be performed was selected because it had the least amount of operation time prior to the due date. Which of the following priority sequencing rules was being used?