APICS CPIM-ECO Question Answer
The best way to determine feasibility of the capacity plan for a work center is to use:
input/output control.
priority sequencing rules.
order management processing.
rough-cut capacity planning.
TESTED 31 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved