You manage a design-build project to renovate a new office space, including infrastructure upgrades.

You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the 60% design phase, the design-build contractor’s project estimate is over budget and contingency. What should be done first to address the issue?

A.

Investigate delaying a portion of the project until additional funding is available.

B.

Pursue a change order from the project sponsor for the difference.

C.

Remove the infrastructure upgrade items from the project scope.

D.

Investigate the reasons for being over budget.