What is a key objective of completing a change management effort?
A.
To provide transition to maintenance and sustaining activities
B.
To assess organizational capacity for change based on this recent project
C.
To determine which mechanisms will be used to prepare the organization for continuous improvement
D.
To revise the performance and reward targets for employees to increase adoption rates
The Answer Is:
A
This question includes an explanation.
Explanation:
Theprimary objective of closureis totransition to maintenance and sustainabilityactivities, ensuring the change becomes part of everyday operations. ACMP explains that this involves transferring ownership to operational leaders, embedding reinforcement mechanisms, and releasing resources. Assessing capacity (B) and preparing for continuous improvement (C) are useful lessons learned, but they are not the closure objective. Revising targets (D) is a tactical step, not a closure requirement. Option A is the correct answer.
(Reference: ACMP Standard, Process Group 5 – Close; Objective: Transition ownership to sustain adoption and benefits.)
CCMP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"