Which statement describes the Monitor Communications process?
A.
Evaluates the differences between the communications management plan and the reality of communications in a project
B.
Ensures that the information needs of the project and the stakeholders are met
C.
Ensures that project information is created, collected, and distributed in a timely and appropriate manner
D.
Develops an appropriate approach and plan for communication of project activities
The Answer Is:
B
This question includes an explanation.
Explanation:
According to the PMBOK® Guide, the Monitor Communications process is the final step in the Project Communications Management knowledge area, occurring within the Monitoring and Controlling process group.
Ensuring Needs are Met (Choice B): This is the formal definition of the process. The primary goal of Monitor Communications is to ensure that the communication requirements of the project and its stakeholders are being satisfied as planned. It involves verifying that the right information reached the right people at the right time and had the desired effect. If the information is not reaching stakeholders or if they are not understanding it, the project manager may need to trigger a change request to modify the communications approach.
Evaluation of Differences (Choice A): While monitoring involves identifying variances between the plan and reality, this is a component of the process rather than the definitive description of the process’s purpose. Choice B is the broader, more accurate PMI definition.
Creation and Distribution (Choice C): This describes the Manage Communications process. Manage Communications is the execution phase where information is actually created and sent out. Monitor Communications happens afterward to check if that distribution was successful.
Developing an Approach (Choice D): This describes the Plan Communications Management process. This is the planning stage where the strategies and templates for communication are first established.
By performing Monitor Communications, the project manager can maintain or increase the efficiency and effectiveness of information flow throughout the project life cycle, ensuring that communication remains a bridge and not a barrier to project success.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"