Projects are undertaken by an organization to support the:
A.
Product performance.
B.
Budget process.
C.
Collective capabilities.
D.
Organizational strategy.
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide and The Standard for Portfolio Management, projects are not isolated activities; they are the primary means by which organizations implement their strategic plans.
Strategic Alignment: Organizations use projects to bridge the gap between their high-level organizational strategy and the actual delivery of business value. Every project should be linked to the organization ' s goals to ensure that resources are being used effectively.
Business Value Creation: Projects are initiated as a result of one or more of the following strategic considerations:
Market demand (e.g., building a new fuel-efficient car).
Strategic opportunity/Business need (e.g., a training company authorizing a project to create a new course to increase its revenue).
Social need (e.g., a non-governmental organization authorizing a project to provide potable water to a community).
Environmental considerations (e.g., a project to reduce a company ' s carbon footprint).
Portfolio Management Link: Projects and programs are often grouped into portfolios specifically to ensure they align with and support the overall organizational strategy and objectives. If a project no longer aligns with the strategy, it is often terminated to redirect resources to more relevant initiatives.
Comparison with other options:
A. Product performance: While a project might improve a product ' s performance, this is a technical objective or a result of a project, rather than the high-level organizational reason why the project was undertaken in the first place.
B. Budget process: The budget process is a functional activity that supports the project by providing funds. Projects are not undertaken to support the budget; rather, the budget exists to support the projects that drive the strategy.
C. Collective capabilities: While projects can enhance the " collective capabilities " of a team or organization (through learning and development), the fundamental driver for initiating a project is to meet a strategic business goal.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"