According to the PMBOKĀ® Guide, a project schedule network diagram is a graphical representation of the logical relationships (dependencies) among the project schedule activities.
Logical Flow: The network diagram is essentially a specialized flow chart that moves from left to right, showing the sequence of work. It uses nodes (representing activities) and arrows (representing logical dependencies) to illustrate how the project " flows " from initiation to completion.
Precedence Diagramming Method (PDM): This is the most common flow chart format used in network diagrams today. It depicts four types of dependencies: Finish-to-Start (FS), Finish-to-Finish (FF), Start-to-Start (SS), and Start-to-Finish (SF).
Purpose: Unlike a standard business flow chart that might show decision loops, a project network flow chart is typically " acyclic " (no loops), focusing on the path required to reach the project finish.
Analysis of Other Options:
B. Control chart: This is a Quality Management tool used to determine whether a process is stable or has predictable performance. It tracks data over time against mean and control limits; it does not show activity sequences or dependencies.
C. Affinity diagram: This is a Data Representation technique used to organize large numbers of ideas into groups for review and analysis (often used after a brainstorming session). It is not used for scheduling or sequencing.
D. Cause-and-effect diagram: Also known as a Fishbone or Ishikawa diagram, this is a root-cause analysis tool used in Quality Management to identify the potential causes of a specific problem. It does not map the chronological flow of project work.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"