The project manager needs to obtain proposals on costs of supplies purchased from an external source. In order to conduct this in a fair and unbiased way, what should the project manager conduct?

A.

Procurement conference

B.

Stakeholder conference

C.

Bidder conference

D.

Stakeholder meeting