PMI CAPM Question Answer
Which of the following tasks is related to the perform qualitative risk analysis process?
Identify the project risks and assign a probability of occurrence
Perform a sensitivity analysis to determine which risk has the most potential for impacting the project
Analyze the effect of identified project risks as numerical data
Prioritize each project risk and assign the probability of occurrence and impact for each one