The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
A.
work package
B.
deliverable
C.
milestone
D.
activity
The Answer Is:
A
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide and the PMI Practice Standard for Work Breakdown Structures, the Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team.
Definition of Work Package: The work package is the lowest level of the WBS. It is the point at which cost and duration for the work can be reliably estimated and managed.
Decomposition: The process of subdivision continues until the deliverables are defined at the work package level. These packages are then typically used to group the activities found in the project schedule, although activities themselves are considered part of the schedule, not the WBS.
Control Accounts: Work packages are often grouped into " Control Accounts " for management and financial reporting, but the work package remains the terminal element of the WBS hierarchy.
Comparison with other options:
B. Deliverable: While the WBS is " deliverable-oriented, " a deliverable can exist at any level of the WBS (including the project level itself). The lowest level specifically is the work package.
C. Milestone: A milestone is a significant point or event in a project. It has zero duration and is a scheduling component, not a level of decomposition in a WBS.
D. Activity: In PMI terminology, activities are the specific actions required to produce a work package. Activities are defined in the Schedule Management processes (Define Activities) and are represented in the project schedule, whereas the WBS stops at the work package level to maintain focus on deliverables.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"