A project team is tasked with decomposing the scope to enable detailed cost and duration...

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.