PMI CAPM Question Answer
Perform Integrated Change Control is the process of:
Reviewing, approving, and managing all change requests
Facilitating change management, manuals, or automation tools
Comparing actual results with planned results in order to expand or change a project
Documenting changes according to the change control system by the change control board