Correlated and contextualized information on how closely the scope is being maintained relative to the...

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.