In the Define Activities process, the schedule management plan is used to:
A.
Capture the lessons learned from other projects for comparison.
B.
Contain the standard activity list.
C.
Document and support the project change requests.
D.
Prescribe the level of detail needed to manage the work.
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide (Project Management Body of Knowledge), specifically within the Project Schedule Management knowledge area and the Define Activities process:
Prescribe Level of Detail (Option D): The Schedule Management Plan is a primary input to the Define Activities process. Its role is to provide the " how-to " for the scheduling processes. Specifically, it prescribes the level of detail necessary to manage the work, including the methodology and the scheduling tool to be used. It sets the criteria for how activities are identified and the degree of decomposition required for the project ' s unique complexity.
Lessons Learned (Option A): While lessons learned are valuable inputs (as part of Organizational Process Assets), they are used to inform the process based on past experiences, but they are not the primary function of the Schedule Management Plan itself.
Standard Activity List (Option B): Standard activity lists are typically part of Organizational Process Assets (OPAs) or templates provided by the performing organization. The Schedule Management Plan guides how these lists are utilized or created but does not " contain " the actual project-specific list.
Change Requests (Option C): Documenting and supporting change requests is the primary function of the Change Management Plan and the Perform Integrated Change Control process. While the schedule management plan may define how schedule changes are managed, it is not the primary document for documenting specific requests.
In the PMI framework, the Schedule Management Plan ensures consistency throughout the project. By prescribing the level of detail during the Define Activities process, the Project Manager ensures that the resulting Activity List is granular enough for accurate estimation and tracking without becoming over-encumbered by unnecessary administrative detail.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"