Given the following information, what is the schedule variance (SV) for this project?

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

A.

5

B.

2

C.

3

D.

4