According to the PMBOKĀ® Guide, the Create WBS (Work Breakdown Structure) process is the process of subdividing project deliverables and project work into smaller, more manageable components.
To perform this process effectively, the Project Scope Statement is a critical input because it contains the detailed description of the project scope and the major deliverables.
Rationale: The Project Scope Statement, along with the Requirements Documentation and the Scope Management Plan, provides the necessary baseline information to begin decomposing the work. Without the detailed description of what needs to be accomplished (found in the Scope Statement), the project team cannot accurately break the work down into work packages.
The Scope Baseline: Once the Create WBS process is complete, the Project Scope Statement, the WBS, and the WBS Dictionary are combined to form the Scope Baseline.
Analysis of Other Options:
A. quality plan: This is an output of the Plan Quality Management process and is generally not an input for creating the WBS.
B. schedule network: This is an output of the Sequence Activities process, which occurs after the WBS has been created and activities have been defined.
C. management document update: These are typically outputs of various processes (including Create WBS) rather than a required input to begin the process.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"