A project manager is reviewing some techniques that can be used to evaluate solution results.

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to evaluate the solution in the larger context to ensure it does not behave in unacceptable ways when deployed to production.

Which evaluation technique should be used here?

A.

Performance testing

B.

Integration testing

C.

Day-in-the-life testing

D.

Exploratory testing