A project is delivering an integrated solution to an external client on a fixed-price contract.

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan