Twenty-five percent of staff turnover is expected.
B.
The technology to be used is cutting-edge.
C.
Project leadership may change due to a volatile political environment.
D.
The product is needed in 250 days.
The Answer Is:
D
This question includes an explanation.
Explanation:
According to the PMBOKĀ® Guide, a Constraint is a limiting factor that affects the execution of a project, program, portfolio, or process. Constraints are often imposed by the organization or by external factors and must be managed by the project manager.
Schedule Constraint: A specific deadline or milestone, such as " The product is needed in 250 days, " is a classic example of a schedule constraint. It limits the project team ' s options regarding duration and resource allocation.
Common Constraints (The Triple Constraint):
Scope: What must be done.
Time/Schedule: Deadlines (like the 250-day requirement).
Cost/Budget: Spending limits.
Other constraints include resources, quality, and risk.
Contrast with Assumptions: While a constraint is a known limitation, an Assumption is a factor that is considered to be true, real, or certain without proof or demonstration.
Analysis of Other Options:
A. Twenty-five percent staff turnover is expected: This is an Assumption or a Risk. It is a factor the team expects to be true, but it is not a predefined limit on how the project must be run.
B. The technology to be used is cutting-edge: This is a Project Characteristic or a Risk. While it influences the project, the " newness " itself isn ' t a restrictive boundary like a budget or a deadline.
C. Project leadership may change...: This is a Risk. It is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives.
CAPM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"