Which of the following will be required to perform simula-tion for schedule risk analysis?

Which of the following will be required to perform simula-tion for schedule risk analysis?

A.

Activity list and activity attributes

B.

Schedule network diagram and duration estimates

C.

Schedule data and activity resource requirements

D.

Milestone list and resource breakdown structure