Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

A.

Schedule Control

B.

Activity Definition

C.

Schedule Development

D.

Activity Resource Estimating