PMI CA0-001 Question Answer
Which of the following project document is best suited for tracking costs of resources?
Work breakdown structure
P'sk breakdown structure
Organizational breakdown structure
Resource breakdown structure
The resource breakdown structure organizes all resources in a hierarchical structure, allowing for cost tracking also.