PMI CA0-001 Question Answer
Create Procurement document is done in _______.
Plan Procurements
Conduct Procurements
Administer Procurements
Close Procurements
Create Procurement document is done in Plan Procurements process.
TESTED 09 Jul 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved