The Business Sponsor threatened to stop funding if there was no evidence of tangible progress.

The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-

rounds of the new bedroom and en-suite bathroom facilities throughout the project.

Is this an appropriate application of Agile Project Management for this project?

A.

Yes, because the early and frequent demonstration of product features to the Business Sponsor increases the visibility of the project and keeps the business engaged.

B.

Yes, because the project's budget holder is the only person who can approve project products.

C.

No, because products should be handed over at the end of the project, during Post-Project.

D.

No, because the Daily Stand-up meetings should have allowed the key representatives to review and discuss the evolving solution.

AgilePM-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now AgilePM-Practitioner pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"