Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both...

Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.

Some members from Marketing and IT, based in India, join via video conferencing.

Issues raised:

. Dependency management challenges

· Concerns about AgilePM principle ' Demonstrate Control '

To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the

issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.

In addition to the Developers, the teams include:

(Developers in the Infrastructure Team report integration issues between climate control and lighting systems, leading to an excessive energy demand beyond the capacity of the solar panels.

Which 2 of the following actions align with the AgilePM guidance on addressing risk?)

A.

Extend the length of the Sprint to allow time to resolve integration issues.

B.

Document all integration risks and have Sukra Aroon decide appropriate mitigation actions.

C.

Add integration testing to acceptance criteria for relevant Backlog items.

D.

Include explicit integration test scenarios in the Sprint Backlog.

E.

Schedule integration workshops at the end of the all Sprints to address any integration concerns.

AgilePM-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now AgilePM-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"