An external web developer is to be contracted to create the new coffee barinsurance area...

An external web developer is to be contracted to create the new coffee bar

insurance area on the existing web site. The chosen web developer will only

agree to work on a 'fixed price for a fixed specification' contract.

What action should the Project Manager take?

A.

Ensure the later elements of the project reflect the most valuable features

of the product being built by the contractor.

B.

Agree to a 'fixed price for a fixed specification' contract with a requirement

for the web developer to provide daily progress reports.

C.

Refuse to employ the chosen web developer as this is not an Agile

approach to project management.

D.

Divide the work into component parts to ensure the web developer is

focused on, and is paid to deliver, only what is specified for each

component.

AgilePM-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now AgilePM-Practitioner pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"