UiPath UiPath-ADPv1 Question Answer
" Process A " is scheduled to run at 2:00 PM using a time trigger with the Schedule ending of Job execution feature configured to stop the job after 20 minutes. Assuming that the robots are busy and " Process A " is queued until 2:05 PM. at what time will " Process A* be stopped?