Test ManagementThe followingchart plots the cumulative number of defects opened against the cumulative number of...

Test Management

The followingchart plots the cumulative number of defects opened against the cumulative number of defects closed during system testing of a software product.

Which of the following statements is true?

Number of correct responses: 1

K21 credit

A.

The chart indicates that you have plenty of problems left to find

B.

The chart can be used to reveal test progress problems

C.

The chart seems to indicate that the defect management process is not working well

D.

The chart seems to indicate that the defect managementprocess is working well

TM12 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now TM12 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"