According to SAFe, what is one approach to retrospectives?
A.
Ensure the event ends with sustainable ideas for the next Iteration
B.
Ensure the event ends with essential working agreements in place for the team
C.
Ensure the event ends with relevant goals for how the team will handle dependencies
D.
Ensure the event ends with actionable improvement items for the backlog
The Answer Is:
D
This question includes an explanation.
Explanation:
According to SAFe®, the Iteration Retrospective is a key event that enables relentless improvement, one of the pillars of the SAFe House of Lean. The purpose is to reflect on the previous iteration and identify what went well, what didn’t, and what can be improved.
An essential outcome of this meeting is a set of actionable improvement items that can be added to the team backlog. These items are often captured as improvement Stories, ensuring that process enhancements are visible, prioritized, and implemented in the next iteration.
From SAFe guidance:
“The retrospective concludes with actionable improvement items added to the backlog. These items should be implemented in subsequent iterations to improve performance.”
Therefore, the correct answer is D. Ensure the event ends with actionable improvement items for the backlog, as it ensures continuous learning and measurable improvement.