During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out sothe Nexus...

During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so

the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on

Team Red completing PBI 1.

All else being equal, which PBI is most concerning?

(choose the best answer)

A.

PBI 2, because it has the most dependencies.

B.

PBI 1, because it is on the top of the Product Backlog.

C.

PBI 1, because it is the first piece of work with a dependency.

D.

PBI 2, because there is a dependency with a different team on work that occurs

within the same Sprint.

SPS PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now SPS pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"