Which two statements describe an Agile Release Train? (Choose two.)
A.
It is the primary value delivery construct in the Scaled Agile Framework
B.
It is used to describe large system behaviors that fulfill Customer needs
C.
It shows the deliverables for the currently committed PI and offers visibility into the next two PIs
D.
It identifies when too much work is in the system which results in multitasking and frequent context switching
E.
It is a long-lived, self-organizing, virtual organization of 5 - 12 Agile Teams that plan, commit, and execute togethe
The Answer Is:
A, E
This question includes an explanation.
Explanation:
An Agile Release Train (ART) is the primary value delivery construct in the Scaled Agile Framework (SAFe). It is a long-lived, self-organizing, virtual organization of 5 - 12 Agile Teams that plan, commit, and execute together. ARTs align teams to a shared business and technology mission and deliver solutions in a value stream with common principles and practices. ARTs are cross-functional and have all the capabilities needed to define, build, test, deploy, release, and operate solutions. ARTs operate on a fixed schedule with common iteration start/end dates and duration, and deliver a new system increment every two weeks. ARTs also plan their work at periodic, mostly face-to-face Program Increment (PI) Planning events, and inspect and adapt at the end of every PI. References: Agile Release Train - Scaled Agile Framework, Essential SAFe - Scaled Agile Framework
SP-SAFe-Practitioner PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"