You are the Scrum Master for your organization and you're training the Product Owner and...

You are the Scrum Master for your organization and you're training the Product Owner and the Development Team on the rules of Scrum. After a few Sprints in the project, the Development Team is getting used to processes and flow of the work. With their confidence, the Development Team has decided that a Sprint Retrospective is no longer needed in the project. What should you do regarding the team's desire to no longer have a Sprint Retrospective?

A.

You should demand the Development Team host a retrospective as it is a rule of Scrum.

B.

You should discuss the situation with the Product Owner to see how she feels about no longer having a Sprint Retrospective.

C.

You should require the key Development Team members to participate in the Retrospective to shorten its duration.

D.

You should do nothing as the Development Team is self-organized and self-managed.

SMC PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now SMC pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"