Scrum SMC Question Answer
Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create
Deliverables process. To do so, they record the impediments in the Impediment Log during
_________________________.
A) Daily Standup Meetings.
B) Sprint Review Meetings.
C) Release Planning Meetings.
D) Sprint Planning Meetings.