John is the Scrum Master for his organization.

John is the Scrum Master for his organization. His current project has one Development Team, but it's been decided to add two more Development Teams. What can John expect for the immediate impact on the existing Development Team's productivity?

A.

Productivity will increase.

B.

Productivity will stay the same.

C.

Productivity will decrease.

D.

It depends on the project's velocity.