A project on developing quality testing equipment for an agro-based industry will start with the...

A project on developing quality testing equipment for an agro-based industry will start with the Create

Deliverables process. Which of the following are NOT inputs to the current process?

A) Scrum Core Team

B) Acceptance Criteria

C) Impediment log

D) Length of Sprint

A.

A and В

B.

B and D

C.

A and C

D.

В and C