A consultant is working on a Service Cloud implementation with a fixed budget and timeline.

A consultant is working on a Service Cloud implementation with a fixed budget and timeline. Additional requirements were discovered early on that will result in the project exceeding timeline and budget constraints.

What is the first step the consultant should take to address the issue?

A.

Document the gap in requirements and discuss the schedule and budget impact with the project team.

B.

Send a change order to the client to account for the additional budget requirements.

C.

Incorporate the additional requirements into the project scope and continue with the original project schedule.

Service-Cloud-Consultant PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now Service-Cloud-Consultant pdf
Get 70% Discount on All Products, Use Coupon: "coponace"