The security team is reviewing whether changes or open issues exist that would affect requirements...

The security team is reviewing whether changes or open issues exist that would affect requirements for handling personal information documented in earlier phases of the development life cycle.

Which activity of the Ship SDL phase is being performed?

A.

Vulnerability scan

B.

Final security review

C.

Open-source licensing review

D.

Final privacy review