Three teams in the Agile Release Train are working on the same Feature.

Three teams in the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, and Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A's piece in the first week of the IP Iteration. Why is this an anti-pattern?

A.

Because Product Management accepted each team's final plan at the end of PI Planning Day 2

B.

Because each feature team needs to integrate with the component team

C.

Because the teams managed their dependencies and planned their integration timing during PI Planning

D.

Because work should not be planned for the IP Iteration

SAFe-SASM PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now SAFe-SASM pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"