They assume a point Solution exists and can be built right the first time
B.
They force design decisions too late in the process
C.
They account for variability inherent in the process
D.
They require the Product Owner to act as gatekeeper or guardian of the process
The Answer Is:
A
This question includes an explanation.
Explanation:
Phase-gate milestones are traditional project management mechanisms that mark the end of one phase and the beginning of another. One major problem with phase-gate milestones is that they assume a point solution exists and can be built correctly the first time. This assumption does not account for the iterative nature of Agile methodologies, where solutions are developed incrementally and iteratively, with feedback loops and continuous improvement. Assuming a point solution can be finalized early often leads to rigidity, lack of adaptability, and higher risks of delivering a product that does not meet the actual needs or expectations.
SAFe-SASM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"