Which statement is true about using a Program Kanban system
A.
All work is visualized, progress is continually tracked
B.
WIP limits are used to provide any needed buffers
C.
Work is pushed through the Kanban to ensure train capacity is utilized
D.
The board tracks features, dependencies and milestones
The Answer Is:
A
This question includes an explanation.
Explanation:
The core principle of a Program Kanban system is the visualization and tracking of work:
All Work Visualized: All work items in progress are represented on the Kanban board, regardless of their nature. This provides complete transparency into what the ART is working on.
Continuous Tracking: Teams update the Kanban board consistently, reflecting the real-time progress of work. This allows anyone to see the current status at a glance.
SAFe-RTE PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"