The amount of Architectural Runway items in the backlog
B.
The number of Story points the combined ART plans for within each Iteration
C.
The number of Features committed to during PI Planning
D.
The system throughput
The Answer Is:
D
This question includes an explanation.
Explanation:
Flow velocity in the context of SAFe is defined as the number of backlog items completed in a given time. It is a measure of the system’s throughput, which reflects how efficiently the Agile Release Train (ART) delivers value. This metric helps teams and organizations gauge their productivity and predictability over time. By tracking flow velocity, ARTs can assess their performance in delivering features, enhancements, and fixes, and make informed decisions to improve their processes and delivery cadence1.
SAFe-RTE PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"